Manufacturing Overview
- Introduction to Manufacturing
- Creating & Managing BOMs
- Work Centers, Capacity & Routing Plans
- Creating, Confirming & Completing MOs
- Production Planning & MRP
- Subcontracting Workflows
- Manufacturing Analysis & Cost Reports
- Unbuild Orders & Reversals
Bills of Materials
Work Centers & Routings
Manufacturing Orders
Planning & Replenishment
Subcontracting
Reporting & Analysis
Production Planning & MRP
Production Planning
Replenishment-Based MO Creation
Products with route "Manufacture" and a reordering rule trigger MO creation:
- Go to Inventory > Master Data > Reordering Rules.
- Set route = Manufacture.
- When stock drops below minimum, the replenishment engine creates an MO.
Planned Orders
Go to Manufacturing > Planning > Planned Orders. These are tentative MOs not yet confirmed. Review and confirm them in batch. Useful for medium-term capacity planning.
MRP (Material Requirements Planning)
For advanced planning:
- Go to Manufacturing > Planning > MRP.
- Click Run MRP.
- Quickenerp analyzes:
- Current stock levels.
- Open sales orders.
- Forecasted demand.
- Reordering rules.
- BOM structure (explodes multi-level BOMs).
- Generates proposed MOs and purchase orders.
- Review and confirm the proposals.
Production Scheduling
The Gantt view in Manufacturing Orders shows scheduled MOs across work centers. Drag and drop to reschedule. Filter by work center, date, product.